Landfill Projects


Listed below are some examples of recent Landfill projects we have completed.


Muskegon County Landfill Cell 6
Location: Revenna, MI
Owner: Muskegon County

27 Acre Cell Construction, Clearing, Geosynthetic Installation, Leachate Collection System, Electrical, Lift Station (inc. Pumps & Controls), Haul Road Construction, Guardrail, 72", 48" & 30" RCP Pipe, topsoil & seeding

Temporary Seeding 12,500 Square Yards
Final Grading 13.55 Acres
Geosynthetics Anchor Trench Excavation and Backfill 2,200 Linear Feet
Supply and Install Secondary and Primary GCL 131,300 Square Yards
Supply and Install Secondary and Primary 60-mil Textured HDPE FML 131,300 Square Yards
Supply and Install Secondary and Primary Double-Sided Drainage Geocomposite 131,300 Square Yards
Supply and Install 1-foot Thick Drainage Sand Layer 42,488 Tons
Supply and Install Leachate Collection Piping, Drainage Media, and Geotextile 6,600 Linear Feet
Supply and Install Leachate Cleanout Risers including Fittings 18 EA
Supply and Install Primary Leachate Conveyance Piping 580 Linear Feet
Electrical System for Secondary Leachate Sideslope Riser 1 EA
Supply and Install Secondary Leachate Conveyance Piping 430 Linear Feet
Leachate Lift Station Construction 1 EA
Leachate Lift Station Electrical and Controls 1 EA
Cell Access Road Construction 1 Lump Sum
Haul Road Construction 1,660 Linear Feet
Supply and Install 30-inch Diameter Culvert with End Sections 140 Linear Feet
Revegetation of Disturbed Areas 19,700 Square Yards


Muskegon County Landfill Phase 4 Final Cover
Location: Revenna, MI
Owner: Muskegon County

26 Acre Final Cover Construction, Waste relocation, 160,000 CY Import soil & Placement, Geosynthetic Installation, Raising Wells, Drain Piping, Berm Construction, Topsoil and Seed/Mulch

Waste Relocation  47,500 Cubic Yards
Extend Existing Leachate Cleanout Risers 36 Each
Recover and Stockpile Existing Road Gravel 850 Cubic Yards
Recover and Install Existing Topsoil 1,030 Cubic Yards
Recover and Install 1.5-foot Thick Granular Fill Protective Layer   10,000 Cubic Yards
Supply and Install 1.5-foot Thick Granular Fill Protective Layer 1,047,080 Square Feet
Expose and Clean Existing Final Cover Liner Tie-In 835 Linear Feet
Expose and Clean Existing Cell Liner Tie-In 3,625 Linear Feet
Supply and Install GCL 1,151,505 Square Feet
Supply and Install 40-mil LLDPE 1,151,505 Square Feet
Supply and Install 2-foot-Thick Granular Fill Erosion Layer 1,209,080 Square Feet
Construct Erosion Control Berms 3,000 Linear Feet
Supply and Install Permanent Erosion Control Blanket 102,000 Square Feet
Haul and Install 0.5-foot Thick Topsoil Vegetative Growth Layer 13,000 Cubic Yards
Supply and Install 0.5-foot Thick Topsoil Vegetative Growth Layer 530,000 Square Feet
Supply and Install Temporary Erosion Control Matting and Establish Vegetation 1,255,000 Square Feet
Remove Existing Litter Control Fence 1 Lump Sum
Supply and Install 6-inch Diameter Perforated PE Drain Pipe with Fabric Sock 3,000 Linear Feet
Supply and Install 6-inch Diameter Solid PE Discharge Pipe 2,250 Linear Feet
Supply and Install Storm Water Drain Piping and Rip Rap Aprons 720 Linear Feet
Fabricate and Install Boots for Penetrations Through Final Cover 38 Each
Extend Existing Gas Wells 15 Each
Extend Existing Condensate Drains 4 Each
Abandon Storm Water Collection Drain 6 Each
Supply and Install 4-inch Diameter Perforated PE Drain Pipe with Fabric Sock 3,625 Linear Feet
Supply and Install 4-inch Diameter Solid PE Discharge Pipe 785 Linear Feet


Oakland Heights Landfill - 2022 Final Cover
Location: Auburn Hills, MI
Owner: Oakland Heights

12 Acre Final Cover Construction, Waste relocation, 75,000 CY Soil Placement, Geosynthetic Installation (by others), Gas Infrastructure Modifications, Storm Water Berm Construction, Down Slope Channels, Topsoil and Seed/Mulch

Stripping/Subgrade Preparation 12 Acres
Grading Layer 10,000 Cubic Yards
18" Compacted Soil Layer 30,673 Cubic Yards
Protective Cover Layer from project stripping 8,400 Cubic Yards
Protective Cover Layer from stockpile 34,083 Cubic Yards
Topsoil Provide 10,821 Cubic Yards
Topsoil Install 10,821 Cubic Yards
Perimeter Termination/Infiltration Water Collection/Outlet Pipe 840 Linear Feet
Expose Cell E-F Liner/Backfill 1,000 Linear Feet
Top Termination Anchor Trench 2,300 Linear Feet
Borrow Area Grading/Seeding 5 Acres
Expose and Clean Final Cover Edge 2,250 Linear Feet
Excavate Excess Soil and Stockpile Adjacent to Work Area 10,000 Cubic Yards
Excavate Waste - Relocate in Work Area or Adjacent Area 10,000 Cubic Yards
Final Cover Transition Soil 4,000 Cubic Yards
Storm Water Diversion Berm, with Geocomposite Outlet 1 Lump Sum
Storm Water Diversion Berm, without Geocomposite Outlet 1 Lump Sum
Storm Water Down Slope Channel 12 Acres
Storm Water Management - CMP Pipe - End Sections 10,000 Cubic Yards
Concrete Lined Ditch 30,673 Cubic Yards
Seed and Mulch - Final Cover Area 8,400 Cubic Yards
Grading, Seed & Blanket - Steep Slope Area - Flex-a-Mat 34,083 Cubic Yards
Storm Water Swale Construction 10,821 Cubic Yards
Raise Existing Gas Extraction Wellhead and Vacuum Lines 10,821 Cubic Yards
Raise Existing Access Risers, Valves, etc. 840 Linear Feet
Adjust Existing Gas System Pipe Grades at Waste Boundary 1,000 Linear Feet
Extend Existing LCS Side Slope Risers 2,300 Linear Feet
Geosynthetic Deployment 5 Acres


Muskegon County Landfill Gas Flare
Location: Revenna, MI
Owner: Muskegon County
Supply & Install 1,000 SCFM Flare    
Supply and Install Temp Flare    
Removal of Old Flare    
Supply & Install  Electrical & Controls System    
New Concrete Pad Extension    
Modifications to Above and Below Grade Pipe Connections    
New Propane Line    
Start-up Services    
Fencing    
Site Restoration    

Michigan's Premier Earthmoving Contractor

Our Location

D&R Earthmoving
10732 Plaza Dr
Whitmore Lake, MI 48189

Map

Phone (517) 306-4933

Email

Hours 8am - 5pm Mon - Fri


DRE Earthmoving

Reviews

“D&R Earthmoving was a great partner in our recent project, working collaboratively with all trades onsite to deliver success. Once they started on site they got right to work, safely and efficiently."
Jacob M.
Project Director
“D&R Earthmoving has been an invaluable partner on some of our more difficult projects. Their field and office operations compliment each other with detailed communication and exceptional performance. Quadrate Construction never worries when D&R Earthmoving is on our projects."
Michael D’A.
Managing Partner
"Just want to pass on a thank you for the extra help you provided today. You guys are doing a great job, and the extra effort today is one of the intangible reasons that we're going to hire you again in the future. Thanks again."
Bart R.
Project Manager
"I would like to take this opportunity to extend our gratitude and thanks for all the help you guys have extended us. We were blessed the day we started the U of M project and were introduced to D&R Earthmoving. Anytime I have called for help you all have been right there. Whenever I call for suggestions you pick up the ball and run with it. Thank you again."
Michael A.
Senior Project Superintendent